1. Naked cooling
(1) After the plate heat exchanger is repaired, a naked cooling test should be carried out, and it should be carried out according to the operation of the equipment maintenance document or the naked cooling plan.
(2) During the naked cold test, check the low-temperature deformation and compensation function of equipment, piping, valves, etc., distinguish whether there is leakage according to the frost situation, and mark the leakage location.
2. Inspection
(1) The plate heat exchanger should be inspected after repair. It is recognized that the repair project has been completed and the repair quality has reached the standard. The repair project should have repair records. When the project is handed over for inspection, the construction unit should provide handover information based on the repair content.
(2) The management site should be kept clean, so that "the work is completed, materials are used up, and the place is clean."
(3) Clean the entire equipment system to ensure that all pipes and valves are clear. All accessories of the equipment should be complete, the surface switching control system should work without obstacles, and the switching valve should be flexible in action.
(4) Load test run inspection, all indicators should meet the required standards. During the inspection, the heat exchanger should be checked for leaks and abnormal noises. If no leaks or medium cross-talk are found, and the temperature and pressure are within the allowable values, then the inspection is qualified. If no abnormalities are found after continuous operation for 24 hours, it can be handed over to production.
After maintenance, it does not mean that there will be no problems. This requires inspection before use. It can only be operated when the inspection confirms that there are no problems. This can also reduce losses.