Installation of stainless steel reactor

       1. The high-pressure stainless steel reactor should be placed indoors. When equipping multiple autoclaves, they should be placed separately. Each operating room should have an exit directly leading to the outdoors or passage, and the equipment location should be well ventilated.
       2. When installing the cauldron cover, the sealing surfaces between the cauldron body and cauldron cover should be prevented from colliding with each other. Carefully place the cauldron lid on the cauldron body in a fixed position. When tightening the main nut, it must be tightened diagonally and symmetrically several times. The force should be even and the cauldron lid should not be allowed to tilt to one side to achieve a good sealing effect.
       3. At the connection between the front and back nuts, only the front and back nuts are allowed to be rotated, and the two arc sealing surfaces are not allowed to rotate relative to each other. When all nut thread connections are assembled, they should be coated with lubricating oil.
       4. The needle valve has a line seal. You only need to gently rotate the valve needle and press the cover tightly to achieve a good sealing effect.
       5. Turn the rotary body on the kettle by hand to check whether the operation is flexible.
       6. The controller should be placed flat on the operating table. Its working environment temperature is 10-40°C, the relative humidity is less than 85%, and the surrounding medium does not contain conductive dust or corrosive gases.
       7. Check whether the movable parts and fixed contacts on the panel and rear panel are normal. Pull off the upper cover and check whether the connector contacts are loose and whether there is any damage or rust caused by improper transportation and storage.
       8. After the operation is completed, it can be cooled naturally, cooled by water, or placed on a stand for air cooling. After the temperature drops, release the pressurized gas in the kettle to reduce the pressure to normal pressure (the pressure gauge shows zero), then loosen the main nut symmetrically and evenly, remove the main nut, and then carefully remove the kettle lid and place it on the stand.
       9. After each operation, the residue on the stainless steel reactor body and lid should be removed. The main sealing port should be cleaned frequently and kept clean. It is not allowed to wipe it with hard objects or rough surfaces.